Mauldlsie WWTW
Full Road and footway Reinstatement including the installation of hell kerbs and bullnose kerbing.
Details
  • Location: Netherhall
  • Duration: 1 month
  • Client: Scottish Water
  • Value: 250k

PROJECT DETAIL

Scope: The treatment works required access from 6am to 5pm every day. The working pattern was changed from 6pm to 2am to complete the works. The Excavation of the main road / entrance / remove of existing road structure down to the solemn then build road make up back up in layers with super enriched surface coating 1000m x 6m. We had to arrange with the local quarries and subsidise them to all access for materials.

Full Road and footway Reinstatement including the installation of hell kerbs and bullnose kerbing.